SUPREME COURT OF INDIA

DHV BV

v.

Tahal Consulting Engineers Ltd. (Israel)

D.K.JAIN, J.

ARBITRATION PETITION NO. 17 OF 2006

SEPTEMBER 12, 2007

 

 

 

Section 11 of the Arbitration and Conciliation Act, 1996 - Arbitrators - Appointment of - Whether it can be laid as an abstract proposition that whenever contracted work is completed, all rights and obligations of parties under contract, ipso facto, come to an end and arbitration agreement also perishes with that contract - Held, no - Petitioner and Respondent No.1 (R-1) were consultant foreign companies - An agreement was signed between R-2 and R-1 with petitioner as sub-consultants for providing management consultancy for water project of R-2 - As per clause 1.10 of agreement R-2 had agreed to bear income-tax liability on payments to be made by it to R-1 through which petitioner, as sub-consultant was to receive all payments-Contract was duly performed and petitioner received last payment in January, 2003 - Subsequently, on receiving notices from Income-tax Department alleging non-payment of tax on remittances made by R-2 under contract, petitioner had to pay additional income-tax demand, to avoid penal consequences - Thereafter, petitioner asked R-1 and R-2 to reimburse amount paid by it - When respondents neither accepted their liability, nor referred matter to arbitration, petitioner filed petition under section 11(6) for appointment of arbitrator - Respondents contended that claim of petitioner was barred by limitation inasmuch as agreement in question was over in March, 2002 and last payment had been made in February, 2003 - Whether since it was obligatory upon R-2 to discharge tax liability in respect of payments made to  sub-consultants and petitioner being a signatory to main contract, claim made by petitioner in respect of income-tax dues would fall within ambit of arbitration agreement between parties - Held, yes - Whether notwithstanding fact that payments against all invoices raised by petitioner stood paid, in light of agreement between parties in terms of clause 1.10, subsequent creation of an additional payment by Income Tax Department in respect of payments made by R-2 to petitioner through R-1 had given rise to a live dispute requiring settlement between parties in terms of arbitration agreement - Held, yes - Whether therefore, petition filed by petitioner was to be allowed - Held, yes

 

 

FACTS

The petitioner was a foreign company providing consultancy and engineering group services with expertise in water management and water planning.  Respondent No.1 (R-1) was also a consultant foreign company based in Israel and respondent No.2 (R-2) was the State Government the Water Resources Organisation.  On 1-12-1997, an agreement was signed between R-1 and R-2, with petitioner and two other concerns, as sub-consultants, for providing management consultancy and technical assistance services for the Tamil Nadu Water Resources Consolidation Project.  As per clause 1.10 of the special conditions of the main contract, R-2 had agreed to bear the Income-tax liabilities on payments to be made by it to the consultant, sub-consultants and their personnel.  Petitioner was to receive all the payments through R-1, being the principal consultant.  The contract was duly performed and petitioner received all payments in respect of the invoices raised by it for the services rendered.  The last payment was received some time in January, 2003.  Thereafter, in February, 2004, the petitioner received notices from the Income-tax Department alleging non-payment of tax on the remittances made by R-2 in respect of said contract.  Though the petitioner paid the additional tax liability raised by the revenue under compulsion to avoid penal consequences but, thereafter in terms of clause 1.10 of the special conditions of the main contract, asked both the respondents to settle the dispute amicably in terms of relevant clause of the general conditions of the main contract.  Both the respondents, however, not only denied their liability to reimburse the amount paid by the petitioner, but also refused to accede to its request demanding reference of the disputes to the arbitration in terms of relevant clause of the main contract.  Consequently, the petitioner filed the instant petition under section 11(6) before the Supreme Court for the appointment of an arbitrator.  The respondents resisted the petition mainly on the grounds that the main contract, under which the petitioner had demanded arbitration, had expired almost four five years prior to the filing of the application and therefore, there was no existing arbitration agreement between the parties.

HELD

The controversy in regard to the nature of function to be performed by the Chief Justice or his designate under section 11 has been set at rest by a Seven-Judge Bench decision of the Supreme Court in the case of SBP v. Patel Engineering Ltd. [2005] 8 SCC 618.  [Para 11]

It is clear from the said judgment that in order to set into motion the arbitral procedure, the Chief Justice or his designate has to decide the issues, if raised, regarding territorial jurisdiction and existence of an arbitration agreement between the parties.  In addition thereto, he can also decide the question whether the claim was a dead one in the sense that the parties have already concluded the transaction by recording satisfaction of their mutual rights and obligations or have recorded satisfaction regarding their financial claims.  Nevertheless, the Supreme Court made it clear that at that stage, it may not be possible to decide whether a live claim made, is one which comes within the purview of the arbitration clause and this question should be lefts to be decided by the arbitral tribunal on taking evidence.  It is, therefore, plain that purely for the purpose of deciding whether the arbitral procedure is to be set into motion or not, the CJ or his designate has to examine and record his satisfaction that an arbitration agreement exists between the parties and that in respect of the agreement, a live issue, to be decided between the parties, still exists.  On being so satisfied, he may allow the application and appoint an arbitral tribunal or a sole arbitrator, as the case may be.  However, if he finds and is convinced that the claim is a dead one or is patently barred by time, he may hold so and decline the request for appointment of an arbitrator.  [Para 12]

Applying those principles on the facts of the instant case, the petition deserved to be allowed.  [Para 13]

Under the special conditions of the contract R-2, as a client, had taken upon itself the obligation to pay on behalf of the consultants, sub-consultants and the personnel any taxes, dues, fees, etc. imposed under the applicable law.  At the same time, as per clause (d) thereof, not only there was an obligation to pay taxes, etc., in certain situations, reimbursement of some of the amounts by the consultants to the client, which the client was compelled to pay, was also postulated.  Obviously, such a situation might arise and that clause would be enforceable even after the expiry of the contract on completion of the services and on the payments having been made.  Therefore, it could not be laid as an abstract proposition that whenever the contracted work is completed, all the rights and obligations of the parties under the contract, ipso facto, come to an end and the arbitration agreement also perishes with the contract.  Each case is required to be considered on its own facts.  In the instant case, though it was true that all the payments were to be made by R-2 to the consultants, but the obligation to pay taxes was also in respect of the payments which were to be received by the sub-consultants, namely, the petitioner in terms of sub-clause (a).  Similarly, the petitioner as well as R-1 were under an obligation to reimburse to R-2 the amount, if any, paid by them in terms of the said clause.  Thus, it was the performance of the contract that ha come to an end, but the contract was still in existence insofar as the dispute arising under clause 1.10 thereof was concerned.  Therefore, there was no merit in the plea of the R-2 that the petitioner had no direct contract with them insofar as the payments of taxes were concerned, and therefore, the dispute raised by them could not fall within the ambit of arbitration agreement between R-2 -the client and R-1 -the consultant or that on completion of the contract, the arbitration clause in the main contract got extinct.  Therefore, an enforceable arbitration agreement existed between the parties.  [Para 14]

The arbitration agreement was in clear terms and brought within its ambit any dispute between the parties as to matters arising pursuant to the main contract which could not be settled amicably.  Admittedly, the liability to pay the taxes flowed from the contract and not otherwise.  Having found that it was obligatory upon R-2 to discharge the tax liability in respect of the payments made to the sub-consultants and the petitioner being a signatory to the main contract, claim made by the petitioner in respect of the income-tax dues would fall within the ambit of the arbitration agreement between the parties.  [Para 16]

As regards the question as to whether the said claim could be said to be stale in the sense that after the last payment in January, 2003, none of the three parties had any pending claims against each other insofar as the payments under the main contract were concerned, notwithstanding the fact that payments against all the invoices raised by the petitioner stood paid, in the light of the agreement between the parties in terms of clause 1.10, subsequent creation of an additional payment by the Income-tax department in respect of the payments made by R-2 to the petitioner through R-1 had given rise to a live dispute requiring settlement between the parties in terms of the arbitration agreement. Consequently, it was axiomatic that prima facie, the claim made by the petitioner was not barred by limitation.  [Para 17]

Therefore, the petition was to be allowed.  [Para 18]